Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 

Two Way Signals | Belvedere Road

There will be two way signals in operation on Belvedere Road from the 25th January to the 7th February 2018 due to work by Fulcrum Pipelines Limited.

 

 

Roadworks | Albert Embankment

From the 15th January 2018 to the 9th February 2018, Transport For London will be carrying out construction work on Albert Embankment, with some carriageway incursion.

Tuesday, 6th February 2018

Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Minor Roadworks | Albert Embankment

Between the 6th and the 9th of February, a lane closure will be in operation on Albert Embankment outside Tintagel House whilst Thames Water undertake work to create a new water connection from the main. This will involve excavating 4m footway and 5m carriageway

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 

Two Way Signals | Belvedere Road

There will be two way signals in operation on Belvedere Road from the 25th January to the 7th February 2018 due to work by Fulcrum Pipelines Limited.

 

 

Roadworks | Albert Embankment

From the 15th January 2018 to the 9th February 2018, Transport For London will be carrying out construction work on Albert Embankment, with some carriageway incursion.

Wednesday, 7th February 2018

Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Minor Roadworks | Albert Embankment

Between the 6th and the 9th of February, a lane closure will be in operation on Albert Embankment outside Tintagel House whilst Thames Water undertake work to create a new water connection from the main. This will involve excavating 4m footway and 5m carriageway

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 

Two Way Signals | Belvedere Road

There will be two way signals in operation on Belvedere Road from the 25th January to the 7th February 2018 due to work by Fulcrum Pipelines Limited.

 

 

Roadworks | Albert Embankment

From the 15th January 2018 to the 9th February 2018, Transport For London will be carrying out construction work on Albert Embankment, with some carriageway incursion.

Thursday, 8th February 2018

Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Minor Roadworks | Albert Embankment

Between the 6th and the 9th of February, a lane closure will be in operation on Albert Embankment outside Tintagel House whilst Thames Water undertake work to create a new water connection from the main. This will involve excavating 4m footway and 5m carriageway

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Utility Works | Upper Ground

From this Thursday 8th February, UKPN will be carrying out utilities works on Upper Ground, underneath Waterloo Bridge. These works are scheduled to take 10 days. The necessary traffic management systems (portable traffic lights) will be put in place either side of the works on Upper Ground and Belvedere Road.

You may encounter delays when trying to use the road, please plan your travel accordingly.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 

Roadworks | Albert Embankment

From the 15th January 2018 to the 9th February 2018, Transport For London will be carrying out construction work on Albert Embankment, with some carriageway incursion.

Friday, 9th February 2018

Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Minor Roadworks | Albert Embankment

Between the 6th and the 9th of February, a lane closure will be in operation on Albert Embankment outside Tintagel House whilst Thames Water undertake work to create a new water connection from the main. This will involve excavating 4m footway and 5m carriageway

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Utility Works | Upper Ground

From this Thursday 8th February, UKPN will be carrying out utilities works on Upper Ground, underneath Waterloo Bridge. These works are scheduled to take 10 days. The necessary traffic management systems (portable traffic lights) will be put in place either side of the works on Upper Ground and Belvedere Road.

You may encounter delays when trying to use the road, please plan your travel accordingly.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 

Roadworks | Albert Embankment

From the 15th January 2018 to the 9th February 2018, Transport For London will be carrying out construction work on Albert Embankment, with some carriageway incursion.

Saturday, 10th February 2018

Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Utility Works | Upper Ground

From this Thursday 8th February, UKPN will be carrying out utilities works on Upper Ground, underneath Waterloo Bridge. These works are scheduled to take 10 days. The necessary traffic management systems (portable traffic lights) will be put in place either side of the works on Upper Ground and Belvedere Road.

You may encounter delays when trying to use the road, please plan your travel accordingly.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 

Sunday, 11th February 2018

Road Closure | Upper Ground

From the 5th to the 23rd March, a road closure will be in effect on Upper Ground between a point 10 metres east of the junction with Cornwall Road and Waterloo Bridge, whilst Lambeth Council undertake carriageway resurfacing works.

Roadworks | Royal Street

Between the 26th January and the 27th April, Lambeth will be undertaking works on Royal Street between Carlisle Lane and Upper Marsh, causing some carriageway incursion. These works are to compound the site for works to Westminster Bridge Road.

Major Works | Albert Embankment

From the 25th January to the 19th February 2018, TFL will be undertaking various major works on Albert Embankment, which will result in delays. Temporary traffic management systems will be in place throughout the duration of the works.

Road Closure | Carlisle Lane

Between the 22nd January and the 30th May, Carlisle Lane will be closed whilst Lambeth undertake works.

Utility Works | Upper Ground

From this Thursday 8th February, UKPN will be carrying out utilities works on Upper Ground, underneath Waterloo Bridge. These works are scheduled to take 10 days. The necessary traffic management systems (portable traffic lights) will be put in place either side of the works on Upper Ground and Belvedere Road.

You may encounter delays when trying to use the road, please plan your travel accordingly.

Roadworks | Parliament Square

From 5th - 26th February, Westminster Council will be carrying out utility works on the roads in and around Parliament Square. Drivers are advised to seek alternative routes via Waterloo Bridge or Vauxhall Bridge. Buses in the area will also be affected

Roadworks | London Road / St Georges Roundabout

From the 28th January - 16th February Thames Water will be undertaking emergency works to unblock a main sewer at the junction of London Road and St Georges Roundabout, near Lambeth Road. This will result in a bus lane closure, in place from 22:00 - 05:00 am between these dates.

Roadworks | Addington Street

TFL  will be carrying out works on Addington Street from the 22nd October 2017 to the 1st March 2018. There will be no carriageway incursion and the working hours will be between 8:00am and 6:00pm

Road Closure | Lambeth Road

There will be a road closure on Lambeth Road, from 29th January to the 12th February due to works being undertaken by Lambeth Council.

 

 