Construction Update | One Blackfriars

Planning permission was granted in 2012  for a 3 buildings consisting of a 170m tower, a 6 storey and 4 storey building with up to 274 flats, retail uses and a hotel.

  • Excavation to B3 – 12 weeks from beginning November 2014 to Feb 2015.
  • Basement levels to be constructed from October 2014 through to April 2015.
  • A 24 hour long concrete pour will take place on 6th to 7th February 2015.
  • The sales pavilion was opened in March 2014.
  • Basement level construction completed April 2015

Construction on this four year project is due to complete in November 2017 with fit out thereafter.