Planning application | Advert Consent - Boots
Address:
37 York Rd, South Bank, London SE1 7NJ, UK
Start date:
31/05/2018
Completion date:
26/07/2018
Update:
An application for advert consent has been submitted for 1No internally fitted Boots lozenge sign above entrance doors (illuminated), 1No pharmacy cross hung internally in window (illuminated), 1No pharmacy cross bus stop sign (illuminated), 1No Pharmacy & 1No Beauty wording internally fitted signs (illuminated), 2No Vinyl Welcome panels, DDA spots to entrance doors at 26 York Road.
More information can be found here
Planning application | Elizabeth House Kiosks
Address:
Cab Rd, South Bank, London SE1, UK
Start date:
15/06/2018
Completion date:
10/08/2018
Update:
A planing application has been submitted for the temporary installation of three kiosks serving coffee, pancakes and donuts located at the side of Elizabeth House for a period of up to three years.
More information can be found on Lambeth’s website, here.
Road resurfacing | Upper Ground
Address:
99 Upper Ground, South Bank, London SE1 9EY, UK
Start date:
18/06/2018
Completion date:
21/06/2018
Update:
Upper Ground will be closed to vehicles between the junction with Cornwall Road and the up ramp to Waterloo roundabout from Monday 18th June to Thursday 21st June. This is to enable that section of Upper Ground to be resurfaced.
Planning Application | Blackfriars Railway Bridge
Address:
1 Blackfriars Bridge, South Bank, London SE1 9UD, UK
Start date:
10/05/2018
Update:
An application has been submitted for the installation of fixtures, fittings and ancillary equipment and associated works to illuminate the bridge in conjunction with the Illuminated River Project. This application is accompanied by an Environmental Statement.
Further details can be found here.
Planning application | Golden Jubilee Bridges
Address:
9152 Golden Jubilee Bridges, London WC2N 6NS, UK
Start date:
30/05/2018
Completion date:
13/08/2018
Update:
A planing application has been received for the architectural illumination, as part of the Illuminated River proposal, of the Golden Jubilee Footbridges, including the installation of fixtures, fittings and ancillary equipment and associated work. (The application is an Environmental Impact Assessment (EIA) development and is accompanied by an Environmental Statement (ES), which may be viewed with the planning application documents).
More information can be found here.
Planning Application | Westminster Bridge
Address:
Westminster Bridge Rd, London SE1, UK
Start date:
08/05/2018
Completion date:
18/07/2018
Update:
An application has been submitted for the architectural illumination, as part of the Illuminated River proposal, of Westminster Bridge including the installation of fixtures, fittings and ancillary equipment and associated works (The application is an Environmental Impact Assessment (EIA) development and is accompanied by an Environmental Statement (ES), which may be viewed with the planning application documents).
The full planning application can be viewed here.
The Listed Building Consent can be viewed here.
Planning application | Waterloo Bridge
Address:
Waterloo Bridge, London, UK
Start date:
23/05/2018
Completion date:
31/07/2018
Update:
A full application and an application for Listed Building Consent has been submitted for the architectural illumination, as part of the Illuminated River proposal, of Waterloo Bridge.
These applications include the installation of fixtures, fittings and ancillary equipment and associated works. (The application is an Environmental Impact Assessment (EIA) development and is accompanied by an Environmental Statement (ES), which may be viewed with the planning application documents).
Listed Building Consent application (reference number 18/01989/LB) can be viewed here.
Full Planning Permission (reference number: 18/01988/FUL) can be viewed here.
Road Closure | Concert Hall Approach
Address:
153 Concert Hall Approach, South Bank, London SE1 8XU, UK
Start date:
16/04/2018
Completion date:
11/05/2018
Update:
From Monday 16 April to Friday 11 May Power On will be carrying out utilities works on Concert Hall Approach.
Further information can be found here.