Major Development | London Television Centre ITV Studio

Address:
London Telivision Centre, Lambeth, London SE1, UK

Start date:
07/09/2017

Completion date:
01/11/2022

Update:

ITV have submitted a planning application for the demolition of existing buildings and the construction of two new buildings (up to 14 storeys and 31 storeys in height with two basement levels) for the provision of circa. 48,069 sq.m of offices and television studios (Use Class B1), 216 sq.m of retail (Use Class A1) and 213 residential dwellings (Use Class C3) with associated vehicle and cycle parking, access works, servicing and landscaping.

The application is accompanied by an Environmental Statement (ES).

[A 6 week consultation period has been allowed for this application. Whilst comments may be accepted beyond this date, please seek to provide comments prior to 6 October 2017 as far as possible to allow sufficient time for officer consideration]

View the full planning application here.

C/W Incursion | Cornwall Road

Address:
21-22 Cornwall Rd, Lambeth, London SE1, UK

Start date:
29/08/2017

Completion date:
01/09/2017

Update:

Some C/W Incursion on Cornwall Road between 29th of August 2017 to 1st of September.

Road Closure | Upper Marsh

Address:
2 Upper Marsh, Lambeth, London SE1, UK

Start date:
11/09/2017

Completion date:
17/11/2017

Update:

From 11th of September – 17th of November,  Upper Marsh will be close.

Road Closure | Carlisle Lane

Address:
219 Carlisle Ln, Lambeth, London SE1 7HJ, UK

Start date:
11/09/2017

Completion date:
17/11/2017

Update:

From 11th of September – 17th of November,  Carlisle Lane will be close

Lane Closure | Mepham Street

Address:
3 Mepham St, Lambeth, London SE1 8FS, UK

Start date:
29/08/2017

Completion date:
30/08/2017

Update:

There will be a lane closure on Mepham Street between 29th and 30th August 2017.

Traffic Management | Chicheley Street 12 Week Programme

Address:
4-5 Chicheley St, Lambeth, London SE1, UK

Start date:
03/08/2017

Completion date:
17/11/2017

Update:

There will be traffic management in place for 12 weeks from the 1st September on Chicheley Street as part of the Southbank Place development.

There will be no lane closures, however the width of the lanes will be reduced to make way for a multi-utility trench which will connect all utilities for the development.

Two way traffic will be maintained throughout the 12 weeks. Works will take place Monday – Friday between 08:00 and 17:00 until 17th November.

The bus stop on Chicheley Street will temporarily suspended for the duration.

Road Closure | York Road

Address:
75-79 York Rd, Lambeth, London SE1 7NJ, UK

Start date:
17/07/2017

Completion date:
29/07/2017

Update:

From 23rd-28th July York Road will be closed to facilitate resurfacing works. The closures will be between 21:00 and 05:00 each night, with the majority of noisy works being completed by 12:00 (midnight). This is part of the ongoing TfL programme for Westminster Bridge Road.

Road Closure | Addington Street

Address:
Park Plaza Westminster Bridge Hotel, 200 Westminster Bridge Rd, Lambeth, London SE1 7UT, UK

Start date:
17/07/2017

Completion date:
29/07/2017

Update:

From 23rd-28th July Addington Street will be closed to facilitate resurfacing works. The closures will be between 21:00 and 05:00 each night, with the majority of noisy works being completed by 12:00 (midnight). This is part of the ongoing TfL programme for Westminster Bridge Road.